Film Call Sheet: How to Create a Professional Daily Call Sheet

The StudioHero's design illustration paper tear effect design white color
Table of Contents

See Studio Hero in Action

Schedule a free demo to manage your entire studio in one place with zero hidden fees.

A film call sheet is a daily production document that tells cast and crew when to report, where to go, and what will be filmed. It includes general crew and individual cast call times, shooting locations, scene schedules, contact information, weather conditions, parking instructions, safety information, and department-specific notes. The assistant director or production team prepares it using the approved shooting schedule.

A call sheet turns the production schedule into practical instructions for a specific shooting day. Instead of requiring everyone to interpret the master schedule, it gives cast, crew, and department heads the information they need to arrive prepared and understand their responsibilities.

An incomplete or outdated call sheet can create confusion before filming even begins. Incorrect call times, missing location directions, outdated scene information, and overlooked safety instructions can affect the entire day’s production.

For this reason, every daily call sheet should be accurate, organized, easy to read, and consistent with the latest approved shooting schedule.

What Is a Film Call Sheet?

A film call sheet is a daily production document distributed to the cast and crew before a scheduled filming day. It communicates reporting times, shooting locations, planned scenes, individual cast requirements, crew assignments, contact information, and other instructions relevant to that day’s production.

A typical film call sheet contains:

  • Production name, shoot date, and production day number.
  • General crew call time and shooting call time.
  • Individual cast call times.
  • Shooting locations and parking instructions.
  • Scene numbers and shooting order.
  • Cast and crew contact details.
  • Weather conditions and sunrise/sunset information.
  • Department-specific instructions.
  • Meal times and transportation arrangements.
  • Emergency contacts and safety information.
  • Estimated wrap time.

The document is generally prepared for the next shooting day and distributed after the production team has confirmed the schedule and relevant departmental requirements.

A call sheet should answer five essential questions:

QuestionInformation required
Who needs to report?Cast, crew, background performers, and department personnel
When must they arrive?General crew call, individual cast calls, department pre-calls, and shooting call
Where must they report?Shooting address, base camp, parking, and department locations
What will be filmed?Scene numbers, descriptions, cast requirements, and shooting order
What should they know?Safety instructions, weather, special requirements, contacts, and production notes

Who Creates a Film Call Sheet?

The Second Assistant Director (2nd AD) commonly prepares call sheets on larger productions, working under the direction of the First Assistant Director (1st AD). The 1st AD oversees the shooting schedule and approves the daily plan before distribution.

The exact responsibility depends on the size and structure of the production. Smaller productions may assign call sheet preparation to the 1st AD, production coordinator, production manager, or producer.

The responsibilities generally include:

Production roleCall sheet responsibility
Second Assistant DirectorPrepares the daily call sheet and coordinates cast and crew reporting information
First Assistant DirectorReviews the daily schedule, confirms shooting requirements, and approves the call sheet
Unit Production ManagerReviews production logistics, costs, resources, and operational requirements
Production CoordinatorHelps organize contact information, logistics, transportation, and document distribution
ProducerOversees production readiness and resolves major operational issues
Department HeadsConfirm department-specific call times, personnel, and requirements

The person preparing the document needs accurate information from the approved shooting schedule, cast availability, locations, transportation, and department heads.

Film Call Sheet vs. Shooting Schedule vs. Stripboard

Although these documents contain related production information, they serve different purposes.

DocumentPurposeTime coverage
Script breakdownIdentifies everything required to film each sceneEntire screenplay
Film stripboardOrganizes scenes into a practical shooting orderEntire production schedule
Shooting scheduleAssigns production dates and planned shooting timesMultiple production days
Call sheetCommunicates the confirmed plan for an upcoming shooting dayOne production day

A shooting schedule may cover several weeks of principal photography. A call sheet focuses on the scenes and instructions relevant to one specific day.

The film script breakdown identifies what each scene requires, while the film stripboard helps determine the shooting order. The approved shooting schedule then provides the information needed to prepare individual daily call sheets.

What Information Should a Film Call Sheet Include?

A professional call sheet should present information in an order that makes it easy for people to find their reporting time, location, schedule, and relevant instructions.

The layout can vary depending on production size, but most film call sheets contain the following sections.

1. Production Information and Header

The header identifies the production and establishes which shooting day the document covers.

Include:

  • Production title.
  • Production company, where applicable.
  • Production date.
  • Shoot day number, such as Day 6 of 20.
  • Director and producer.
  • First Assistant Director.
  • Second Assistant Director.
  • Unit Production Manager.
  • Production office contact information.
  • Call sheet version or revision identifier.

The production day number is particularly useful because it distinguishes the filming schedule from the calendar date.

For example, a call sheet might identify Thursday, October 15, as Day 7 of 22. This helps everyone reference the same point in the production schedule.

2. General Crew Call and Shooting Call Times

The call sheet should distinguish between different reporting times.

These times are not necessarily the same for everyone.

Call timeMeaning
General crew callThe main reporting time for most crew members
Department pre-callAn earlier reporting time for departments that need additional preparation
Cast callThe reporting time assigned to an individual performer
Makeup and wardrobe callThe time a performer must report for preparation
On-set callThe time a performer must be ready on set
Shooting callThe planned time for filming to begin
Estimated wrapThe expected end of the shooting day

Consider a production where the crew needs to prepare lighting and camera equipment before the first scene.

The general crew call might be 6:30 AM, while the shooting call is 8:00 AM. A principal actor may have an individual call at 7:00 AM, followed by makeup, wardrobe, and an on-set call at 7:45 AM.

These times should be coordinated with the actual preparation requirements of each performer and department.

3. Shooting Location and Base Camp Details

Location information must be precise enough for cast and crew to reach the correct reporting point without additional clarification.

Include:

  • Primary shooting location name.
  • Complete street address.
  • Location entrance or reporting point.
  • Base camp address.
  • Parking arrangements.
  • Crew transportation instructions.
  • Equipment loading and unloading areas.
  • Holding areas, where applicable.
  • Restroom and catering locations.
  • Contact person for location-related questions.

When the shooting location and base camp are different, list both addresses separately.

For productions using multiple locations on the same day, identify the relevant address for each scene and explain when the company is expected to move.

A map or location reference can also help when filming at large facilities, remote sites, or locations with restricted access.

4. Weather, Sunrise, and Sunset Information

Weather information is particularly important for exterior scenes and productions working in changing environmental conditions.

A call sheet should include:

InformationWhy it matters
Weather forecastHelps departments prepare for expected conditions
TemperatureSupports wardrobe and environmental preparation
Rain probabilityHelps assess exterior shooting conditions
Wind conditionsRelevant for lighting, camera rigs, and outdoor setups
SunriseHelps plan early exterior photography
SunsetHelps determine available natural daylight
Special weather warningsIdentifies conditions requiring additional precautions

The weather information should correspond to the actual shooting location and production date.

For night shoots, early morning calls, or exterior photography, sunrise and sunset information is especially useful.

5. Emergency Contacts and Safety Information

A call sheet should contain emergency information relevant to the day’s shooting activities.

This section may include:

  • Nearest suitable hospital or emergency department.
  • Hospital street address.
  • Emergency contact information.
  • On-set medic or medical professional.
  • Production safety contact.
  • Special hazard information.
  • Emergency access instructions.
  • Applicable evacuation or assembly information.

Safety notes should be specific to the day’s activities.

For example, an exterior shoot near a public road may require traffic-control information. A scene involving stunts, firearms, water, animals, or elevated platforms may need additional safety instructions and relevant departmental contacts.

The call sheet should reflect the actual risks and arrangements for that shooting day rather than repeating generic safety statements.

6. Daily Shooting Schedule

The daily shooting schedule is one of the most important parts of the call sheet.

It identifies the scenes planned for the day and the order in which the production expects to film them.

A typical scene schedule includes:

FieldInformation
Scene numberOriginal screenplay scene number
Set / locationWhere the scene will be filmed
Scene descriptionBrief explanation of the action
INT./EXT.Interior or exterior
Day / NightStory time designation
Page countLength of the screenplay scene
Cast IDsPrincipal performers required
Planned timeEstimated shooting time or sequence
Special notesScene-specific production requirements

The scene order should match the approved shooting schedule.

When the company moves between locations, show the move clearly so departments understand where and when they need to relocate.

7. Cast Information and Individual Call Times

The cast section identifies the performers required for the shooting day and their individual reporting requirements.

Unlike a general crew call, cast members may have different arrival times depending on their scenes and preparation needs.

A cast grid commonly includes:

  • Cast identification number.
  • Actor’s name.
  • Character name.
  • Individual call time.
  • Pickup time, where applicable.
  • Makeup and hair call.
  • Wardrobe call.
  • On-set time.
  • Scenes required.
  • Status or availability notes.

Some productions use cast status codes to communicate an actor’s work requirements.

CodeCommon meaning
SStart
WWork
HHold
FFinish

These codes should be accompanied by a clear legend because specific conventions may differ between productions.

Cast identification numbers should match the numbers appearing in the scene schedule and relevant production records.

8. Extras and Background Performers

Background performers require their own reporting information when they are needed for a shooting day.

This section may include:

  • Number of background performers.
  • Type of background role.
  • Individual or group call time.
  • Wardrobe requirements.
  • Makeup and hair requirements.
  • Holding location.
  • Scene assignments.
  • Special instructions.

For example, a restaurant scene may require 15 background performers dressed as customers. The call sheet should identify their reporting arrangements, holding area, preparation requirements, and assigned scenes.

9. Crew List and Department Call Times

The crew section communicates reporting requirements for the production departments.

Typical information includes department, crew member name, contact details, and call time.

DepartmentTypical information
ProductionProduction office, coordinators, and assistants
CameraDirector of Photography, camera operators, assistants
Grip and ElectricLighting and rigging personnel
SoundProduction sound mixer and boom operators
Art DepartmentProduction design, set decoration, and props
CostumeWardrobe supervisor and assistants
Makeup and HairMakeup artists and hair stylists
LocationsLocation manager and assistants
TransportationDrivers and transportation coordinators
CateringCatering personnel and meal arrangements

Not every production needs every department listed separately. The call sheet should reflect the actual crew structure and reporting requirements for the day.

10. Department Notes and Special Instructions

Department notes communicate work-specific information that may not be obvious from the main schedule.

For example:

  • Camera: Specialist camera setup required for the opening scene.
  • Art Department: Final dressing and set preparation before crew call.
  • Wardrobe: Continuity costume required for Scene 14.
  • Props: Picture vehicle and hero prop required before filming.
  • Locations: Restricted access to the secondary entrance.
  • Sound: Playback preparation required before the first take.
  • Transportation: Shuttle departure time from base camp.

Keep instructions relevant to the department receiving them. Detailed technical information that requires a separate document should be provided through the appropriate production paperwork.

11. Meals, Breaks, and Transportation

The call sheet should communicate practical arrangements that affect the working day.

Include information about:

  • Breakfast availability.
  • Estimated lunch time.
  • Catering location.
  • Meal arrangements for location moves.
  • Transportation pickup points.
  • Shuttle departure times.
  • Parking restrictions.
  • Vehicle staging.
  • Estimated wrap arrangements.

Meal timing should reflect the actual shooting plan and the applicable production agreements and requirements.

12. Advance Schedule and Next-Day Information

Some productions include an advance schedule that gives cast and crew an early view of the following shooting day.

It may contain:

  • Upcoming production date.
  • Expected general crew call.
  • Planned shooting location.
  • Preliminary scenes.
  • Known location changes.
  • Important preparation requirements.

The advance schedule is preliminary information, not a replacement for the approved call sheet for that day.

How to Create a Film Call Sheet Step by Step

Preparing a call sheet requires coordinating information from the shooting schedule, cast, crew, locations, transportation, and department heads.

The following process helps maintain accuracy across those inputs.

Step 1: Start With the Approved Shooting Schedule

Begin with the latest approved shooting schedule and identify the scenes planned for the upcoming production day.

Confirm:

  • Scene numbers.
  • Scene descriptions.
  • Shooting order.
  • Location requirements.
  • Cast members required.
  • Script page counts.
  • Day and night designations.
  • Company moves.

Do not prepare the call sheet from an outdated schedule or an informal list of planned scenes.

Step 2: Confirm the Production Date and Shooting Day

Enter the actual production date and day number.

For example:

Shoot Date: October 15

Production Day: Day 7 of 22

Confirm that the production date matches the current schedule and that the correct shooting day number is displayed.

This distinction becomes particularly important when the production includes weekends, holidays, weather delays, or schedule changes.

Step 3: Confirm the Location and Reporting Instructions

Add the shooting address, base camp, parking location, and reporting instructions.

Contact the location department to verify access arrangements and any restrictions affecting arrival or transportation.

For a location with multiple entrances, provide the correct reporting point rather than relying on the general street address alone.

Step 4: Establish General Crew and Shooting Call Times

Confirm the general crew call and planned shooting call with the First Assistant Director and relevant department heads.

Work backward from the planned first shot to establish realistic preparation times.

For example:

TimeActivity
6:30 AMGeneral crew call
6:45 AMDepartment preparations
7:00 AMPrincipal cast call
7:00 AMMakeup and wardrobe preparation
7:45 AMFirst cast members ready on set
8:00 AMShooting call

The example is illustrative. Actual times depend on the number of setups, cast preparation, location access, and department requirements.

Step 5: Add Individual Cast Calls

Review the shooting schedule and identify every performer required for the day’s scenes.

Confirm each person’s call time, pickup arrangement, makeup requirements, wardrobe preparation, and scheduled scenes.

Check for actors appearing in multiple scenes with different preparation needs.

An actor required only for an afternoon scene should not automatically receive the general crew call time. Individual calls should reflect actual production requirements and any applicable contractual restrictions.

Step 6: Add the Crew and Department Requirements

Collect confirmed department call times and personnel information.

Check whether any departments require an early pre-call because of equipment setup, lighting preparation, location preparation, or specialist requirements.

Department heads should verify that the listed people, responsibilities, and arrival times are accurate.

Step 7: Complete the Daily Scene Schedule

Transfer the approved scenes into the call sheet in their planned shooting order.

Confirm page counts, cast identification numbers, locations, and special requirements against the latest schedule.

If the production includes a company move, show the relevant location transition and allow for the time needed to relocate.

Step 8: Add Weather, Emergency, Meal, and Safety Information

Check the weather for the correct location and shooting date.

Record sunrise and sunset times when relevant, confirm the nearest hospital and emergency arrangements, and include any location-specific hazards or safety instructions.

Add meal estimates, catering arrangements, parking instructions, and transportation details.

Step 9: Review the Call Sheet With the Production Team

Before distributing the document, review it against the approved shooting schedule.

The First Assistant Director and relevant production personnel should check the information that affects their responsibilities.

Pay particular attention to cast calls, location access, daily scenes, department reporting times, safety information, and company moves.

Step 10: Distribute the Approved Call Sheet

Once reviewed and approved, distribute the call sheet through the production’s designated communication channel.

The distribution list should include the cast and crew members who need the information for that shooting day.

On many productions, the call sheet is distributed the evening before filming, giving everyone time to review their instructions and prepare.

When revisions become necessary, issue a clearly identified updated version and make sure recipients know which document is current.

Film Call Sheet Example: A Daily Shooting Schedule

Consider a fictional independent film shooting at a roadside diner.

The production has two scenes scheduled for the day, with principal cast, a small crew, and background performers.

The following example demonstrates how the information can be organized into a daily call sheet.

Production Header

FieldExample information
ProductionThe Last Stop
Production DayDay 6 of 18
Shoot DateOctober 15
DirectorAlex Morgan
ProducerJordan Reed
First Assistant DirectorTaylor Brooks
General Crew Call6:30 AM
Shooting Call8:00 AM
Estimated Wrap7:00 PM
Meal1:00 PM

Location and General Information

FieldExample information
Main LocationRiverside Diner
Address125 Main Street, Example City
Base CampRear parking area
Crew ParkingDesignated production parking area
Nearest HospitalExample Regional Medical Center
WeatherCloudy, possible afternoon rain
Sunrise6:45 AM
Sunset6:10 PM

The example uses fictional production and location information.

Daily Scene Schedule

SceneDescriptionINT./EXT.D/NPagesCast
22Lena meets Daniel inside the dinerINT.DAY1 1/81, 3
23Lena leaves the diner after the conversationEXT.DAY6/81, 3

Cast Calls

Cast IDActorCharacterCallMakeup / WardrobeScenes
1Emma CarterLena7:00 AM7:00 AM22, 23
3Noah BennettDaniel7:15 AM7:15 AM22, 23

Crew Calls

DepartmentPersonnelCall Time
CameraCamera team6:30 AM
Grip and ElectricLighting team6:30 AM
SoundSound team6:30 AM
Art DepartmentSet dressing team6:30 AM
Makeup and HairMakeup team7:00 AM
WardrobeCostume team7:00 AM
LocationsLocation team6:00 AM

Department Notes

DepartmentInstructions
CameraPrepare the interior and exterior camera setups
Art DepartmentComplete diner dressing before shooting call
PropsPrepare table dressing and scene-specific props
WardrobeMaintain continuity between both scenes
LocationsConfirm access and crew parking
TransportationKeep designated production vehicles available

Safety and Production Notes

  • Confirm weather conditions before exterior photography.
  • Keep emergency access clear.
  • Confirm the nearest hospital and production safety contact.
  • Follow location-specific traffic and parking arrangements.
  • Keep production areas clear of unauthorized personnel.

This example illustrates the relationship between the shooting schedule, cast reporting requirements, department preparation, and daily production instructions. A real call sheet should contain verified names, contact numbers, addresses, and emergency arrangements.

Common Film Call Sheet Mistakes to Avoid

A call sheet can contain all the standard sections and still create production problems when the information is inaccurate or unclear.

1. Using Incorrect Call Times

Different people may have different reporting requirements. Giving everyone the general crew call can result in unnecessary waiting, while assigning an actor an unrealistic preparation window can delay the first scene.

Verify individual cast calls, department pre-calls, and shooting call times separately.

2. Using an Outdated Shooting Schedule

When the shooting order changes, the call sheet must reflect the revised scene schedule.

An outdated document can send cast and crew to the wrong location or leave a department unprepared for a scene’s requirements.

3. Providing Incomplete Location Details

A street address alone may not identify the correct entrance, parking area, or base camp.

Include the actual reporting point and relevant location instructions.

4. Missing Individual Cast Requirements

The cast section should reflect individual pickup, makeup, wardrobe, and on-set requirements where applicable.

Do not assume everyone has the same call time or preparation needs.

5. Leaving Out Safety Information

Emergency contacts, the nearest suitable hospital, and hazards relevant to the shooting day should not be overlooked.

A generic safety note does not replace specific information about the day’s activities and location.

6. Forgetting Company Moves

When the production is filming at multiple locations, show the move clearly and communicate the arrangements to the affected departments.

7. Making the Call Sheet Difficult to Read

Avoid unnecessary paragraphs, inconsistent formatting, overcrowded tables, and unclear abbreviations.

People should be able to locate their individual call time, location, and department instructions quickly.

8. Distributing Conflicting Versions

When a call sheet is revised, identify the new version and communicate that it replaces the previous one.

The cast and crew should not have to guess which document contains the approved information.

Film Call Sheet Quality-Control Checklist

  • Production title, date, and shooting day number are correct.
  • The latest approved shooting schedule has been used.
  • General crew call and shooting call are clearly distinguished.
  • Individual cast call times are confirmed.
  • Makeup, wardrobe, and on-set times are included where required.
  • All scheduled scenes appear in the correct shooting order.
  • Cast identification numbers match the scene schedule.
  • Shooting addresses, base camp, and parking instructions are accurate.
  • Department personnel and reporting times are verified.
  • Weather and sunrise/sunset information are current.
  • Emergency contacts and nearest hospital information are included.
  • Day-specific safety instructions are documented.
  • Meals, transportation, and company moves are accounted for.
  • Department notes reflect actual shooting requirements.
  • Estimated wrap and daily schedule have been reviewed.
  • The First Assistant Director or designated authority has approved the document.
  • The correct version has been distributed to the relevant cast and crew.

How Studio Hero Can Help with Film Production Coordination

A daily call sheet communicates the operational requirements of a shooting day. Production teams also need their project information, scheduled activities, people, resources, and supporting records to remain connected as the production moves forward.

Studio Hero’s Production Management feature connects Productions, Projects, Events / Sessions, and Tasks. Projects bring together operational information including scheduled activities, talent, resources, media, files, rates, and financial context.

Connect Production Activities With Daily Call Sheets

Studio Hero includes call sheet inclusion rules within its production workflow. Events and resources can be included in call sheets, connecting scheduled production activities and their associated resource information with daily production documentation.

This helps keep relevant operational information connected to the production rather than treating every scheduled activity as an isolated record.

Keep Production Schedules and Resources Connected

Studio Hero’s Studio Scheduling connects production activities with rooms, people, equipment, and services.

Production teams can manage the scheduling and availability of shared resources across projects and scheduled work, helping coordinate the operational requirements behind each shooting day.

Maintain Connected Production Projects

Studio Hero’s Production Management feature organizes production-level work through connected projects, Events / Sessions, tasks, resources, and supporting information.

For production companies managing multiple projects, this structure provides a connected way to organize operational activities and maintain visibility across production work.

Studio Hero’s Film & Video Production Management Software brings these production management and scheduling workflows together for film and video production teams.

Wrapping Up

A professional film call sheet gives cast and crew a clear understanding of the next shooting day’s schedule, reporting requirements, location information, and production instructions.

Preparing an accurate call sheet requires more than copying scenes from a shooting schedule. The production team must confirm individual call times, coordinate department requirements, verify locations, document safety information, and ensure that every detail reflects the latest approved production plan.

When call sheets remain consistent with the shooting schedule and production requirements, the entire team can prepare for each day with fewer communication gaps and a clearer understanding of the work ahead.

Keep reading

thestudiohero.com
Daily Production Report: What to Track Every Shooting Day

A daily production report (DPR) is a document that records what actually happened during a film or video production day.

thestudiohero.com
Day Out of Days (DOOD) Report: How to Create and Read a Film DOOD Schedule

A Day Out of Days (DOOD) report is a film production scheduling document that tracks when each cast member is

thestudiohero.com
Film Call Sheet: How to Create a Professional Daily Call Sheet

A film call sheet is a daily production document that tells cast and crew when to report, where to go,