A Day Out of Days (DOOD) report is a film production scheduling document that tracks when each cast member is required throughout the shooting schedule. It uses a grid to display working days, hold days, start dates, and finish dates for every performer. Production teams use it to review cast availability, identify scheduling gaps, and evaluate the financial impact of performer engagements.
A film schedule shows which scenes are planned for each shooting day. A DOOD report takes that information and presents it from the cast member’s perspective, showing exactly when each performer starts working, when they are needed, and when their engagement ends.
This distinction matters in productions with multiple cast members, overlapping scenes, and complicated shooting schedules. An actor may work on Monday, remain on hold for two days, return on Thursday, and finish on Friday. Reviewing individual scene schedules alone makes these gaps harder to identify.
A DOOD report brings that information together in one place, giving assistant directors, production managers, producers, and production accountants a clearer view of cast scheduling and engagement requirements.
What Is a Day Out of Days (DOOD) Report?
A Day Out of Days report, commonly abbreviated as DOOD, is a grid-based scheduling document used in film and television production to track the working status of cast members across the entire production schedule.
Each row represents a cast member, while each column represents a shooting day or calendar day. The corresponding cells contain status codes that indicate whether a performer is starting work, actively working, on hold, traveling, or finishing their engagement.
A typical DOOD report includes:
- Cast identification numbers and character names.
- Shooting dates and production day numbers.
- Start Work and Work statuses.
- Hold days between scheduled workdays.
- Work Finish and Start Work Finish dates.
- Travel, rehearsal, and other applicable statuses.
- Total working days and hold days.
- First and last engagement dates.
The report is primarily used for cast scheduling, but some production scheduling systems can also generate similar reports for extras, stunts, vehicles, props, special effects, costumes, and other production elements.
The Movie Magic Scheduling documentation describes DOOD as a report showing when production elements are expected to work throughout a production.
Why Is a DOOD Report Important?
A shooting schedule may show that an actor is needed on five different days, but it does not necessarily make the gaps between those days obvious.
Those gaps can affect cast engagement, contractual obligations, scheduling decisions, and production expenses.
For example, consider an actor scheduled to work on Monday, Tuesday, and Friday. The actor may need to remain available on Wednesday and Thursday, depending on the production’s agreement and scheduling arrangements.
Without a consolidated DOOD, the production team may have to examine several shooting schedules or daily call sheets to understand the actor’s complete engagement.
A DOOD report makes the situation visible immediately.
| Production concern | How a DOOD report helps |
|---|---|
| Cast availability | Shows when performers are required throughout the production |
| Hold days | Identifies non-working days between scheduled engagements |
| Cast scheduling | Helps identify performers with overlapping or extended requirements |
| Engagement duration | Shows the first and last scheduled working dates |
| Production costs | Makes potential hold and engagement costs easier to evaluate |
| Schedule revisions | Shows which cast members may be affected when scenes move |
| Production coordination | Provides a consolidated view of cast requirements across shooting days |
The report supports scheduling decisions, but it does not replace performer contracts, deal memos, payroll records, or applicable union and guild requirements.
DOOD Report vs. Shooting Schedule vs. Call Sheet
A DOOD report is closely connected to the shooting schedule and call sheets, but it is not a replacement for either document.
Each serves a different production requirement.
| Document | What it tracks | Primary purpose |
|---|---|---|
| Shooting schedule | Scenes and shooting days | Establishes when scenes will be filmed |
| Stripboard | Scene strips and shooting order | Organizes scenes into production days |
| DOOD report | Cast working status across production days | Tracks performer engagements and hold periods |
| Call sheet | Daily cast and crew reporting requirements | Communicates instructions for the next shooting day |
A stripboard provides the scene order, the shooting schedule assigns those scenes to dates, and the DOOD translates the resulting schedule into cast-specific working patterns.
The film stripboard is therefore an important starting point for creating a reliable DOOD report.
A call sheet serves a different purpose. It provides the individual reporting information required for a specific shooting day, while the DOOD shows the wider cast schedule across the production.
Who Prepares a Day Out of Days Report?
The First Assistant Director (1st AD) generally oversees the shooting schedule and the related cast scheduling information. Depending on the production, the Second Assistant Director (2nd AD), production coordinator, Unit Production Manager (UPM), or production accountant may also prepare, review, or maintain the DOOD report.
The responsibilities can be divided as follows:
| Production role | DOOD-related responsibility |
|---|---|
| First Assistant Director | Oversees the shooting schedule and reviews cast scheduling requirements |
| Second Assistant Director | Helps maintain daily cast scheduling and related production information |
| Unit Production Manager | Reviews production logistics, performer engagement requirements, and financial implications |
| Production Coordinator | Organizes scheduling information and maintains production documentation |
| Production Accountant | Reviews engagement information against contracts, payroll requirements, and production costs |
| Producer | Reviews the wider production schedule and budget implications |
On smaller productions, these responsibilities may be handled by fewer people. The important requirement is that the DOOD remains consistent with the approved shooting schedule and the information used by production management and accounting.
Understanding DOOD Codes and Abbreviations
DOOD reports use short codes to communicate cast scheduling statuses. These codes make it possible to review a large number of performers and shooting days without writing lengthy descriptions in every cell.
However, terminology and available codes can vary between production scheduling systems. The following table describes commonly used conventions.
| Code | Full form | Meaning |
|---|---|---|
| SW | Start Work | The performer’s first scheduled working day |
| W | Work | A day when the performer is scheduled to work |
| WF | Work Finish | The performer’s final scheduled working day |
| SWF | Start Work Finish | The performer starts and finishes work on the same day |
| H | Hold | A non-working day between scheduled engagements when the performer remains held |
| D | Drop | The performer is released rather than remaining on hold |
| PW | Pick-Up Work | The performer returns to work after a drop |
| T / TR | Travel | A scheduled travel day |
| R | Rehearsal | A day scheduled for rehearsal rather than regular filming |
Some systems also use codes such as F for Finish, FT for Fitting, M for Company Move, or combined codes such as SWD and PWF.
The exact legend should always be checked against the scheduling software and production’s established reporting conventions. The Movie Magic DOOD manual provides additional details about its status codes and scheduling rules.
SW: Start Work
SW identifies the first scheduled working day for a performer.
For example, when an actor begins filming on Production Day 1 and continues working on subsequent days, the first cell is marked SW.
It establishes the beginning of the performer’s scheduled engagement in the DOOD.
W: Work
W represents a normal scheduled working day after the performer has started work.
If an actor works on Days 2, 3, and 4 following a Start Work entry on Day 1, those days are recorded as W.
These entries help production teams calculate the number of scheduled workdays.
WF: Work Finish
WF represents the performer’s final scheduled working day.
For example, an actor who starts on Day 1, works through Day 4, and has no further scheduled work would receive WF on Day 4.
It identifies the end of the performer’s scheduled work.
SWF: Start Work Finish
SWF is used when a performer is required for just one working day.
For example, a day player appearing in a single scene may receive an SWF entry on Day 3.
This indicates that the performer’s first and last working day occur on the same date.
H: Hold
A hold day is a non-working day between scheduled workdays when a performer remains engaged or reserved for the production.
Consider an actor who works on Monday and Tuesday, is not required on Wednesday, and returns on Thursday.
Wednesday may be recorded as H if the performer remains held under the applicable arrangement.
Hold days are important because they can create financial obligations even when the performer is not filming.
The financial treatment of a hold depends on the performer’s contract, applicable union or guild agreement, and production arrangements. A DOOD makes the scheduling gap visible, but the production accountant must verify the actual payment requirements.
D and PW: Drop and Pick-Up Work
A drop indicates that a performer is released during a gap rather than remaining continuously held.
If the production needs that performer again later, the subsequent engagement can be represented using a Pick-Up Work entry.
For example:
- Day 1: SW
- Day 2: W
- Day 3: D
- Days 4 to 8: Released
- Day 9: PW
- Day 10: WF
This distinction can be important when reviewing extended gaps between cast engagements. Whether a drop is permitted and how it affects payment must be checked against the applicable contract and production agreement.
T and R: Travel and Rehearsal
Some productions use separate entries for travel and rehearsal requirements.
A travel day indicates that the performer is scheduled to travel for production purposes. A rehearsal day indicates a scheduled rehearsal rather than a normal filming day.
These activities can affect engagement arrangements and should be represented consistently when the production’s DOOD format supports them.
How to Create a Day Out of Days Report Step by Step
A DOOD report should be prepared using the approved shooting schedule. It should not be created independently from the screenplay because the cast’s actual working pattern depends on which scenes are assigned to which production days.
Step 1: Finalize the Shooting Schedule
Start with the approved stripboard and shooting schedule.
Confirm the following information:
- Production dates.
- Shooting day numbers.
- Scene numbers.
- Scene order.
- Cast requirements for every scene.
- Planned company moves.
- Rest days and non-shooting days.
The schedule must be sufficiently stable for cast requirements to be reviewed accurately.
If scenes are moved after the DOOD is prepared, the affected cast entries must be reviewed and updated.
Step 2: Prepare the Cast List
Create a master list of all performers involved in the production.
Assign each cast member a unique identification number and connect that number with the appropriate character name.
For example:
| Cast ID | Character | Cast classification |
|---|---|---|
| 1 | Lena | Principal cast |
| 2 | Mark | Principal cast |
| 3 | Daniel | Supporting cast |
| 4 | Sarah | Supporting cast |
| 5 | Taxi Driver | Day player |
The cast identification numbers should match those used in the script breakdown and stripboard.
This makes it easier to identify which performers are required in each scene and transfer that information into the DOOD.
Step 3: Create the Production Day Grid
Set up the DOOD with shooting days arranged horizontally and cast members listed vertically.
Each column represents a production day, while each row represents a performer.
Include the calendar date and production day number so the information can be matched against the shooting schedule.
A basic structure looks like this:
| Cast member | Day 1 | Day 2 | Day 3 | Day 4 | Day 5 | Day 6 |
|---|---|---|---|---|---|---|
| Lena | SW | W | H | W | W | WF |
| Mark | SW | W | WF | – | – | – |
| Daniel | – | – | SWF | – | – | – |
| Sarah | – | SW | W | WF | – | – |
The grid provides a starting point for recording the individual working patterns of the cast.
Step 4: Transfer Cast Requirements From the Shooting Schedule
Review every shooting day and identify the performers required for the scheduled scenes.
Use the cast identification numbers to match each scene with its corresponding performers.
For example, when Scene 12 requires Lena and Mark, both performers should receive the appropriate working status for that shooting day.
Repeat this process across the entire schedule.
Do not populate the DOOD based only on the actor’s overall appearance in the screenplay. The report must reflect the actual scheduled shooting dates.
Step 5: Assign Start, Work, and Finish Codes
After transferring the cast requirements, assign the appropriate codes.
A typical sequence might look like:
SW → W → W → WF
This indicates that the performer starts work on the first day, continues working for two more days, and finishes on the fourth day.
For a performer required on only one day:
SWF
The first and last working days should be checked against the full schedule to avoid incorrect engagement dates.
Step 6: Identify Hold Days
Compare each performer’s first and last scheduled working days.
Identify non-working days that fall between those dates and determine whether the performer remains held.
For example:
| Production day | Cast requirement |
|---|---|
| Day 1 | SW |
| Day 2 | W |
| Day 3 | H |
| Day 4 | W |
| Day 5 | WF |
This performer has four working days and one hold day.
A hold should not be assigned automatically to every non-working day. The production must check the performer’s actual engagement and applicable contract.
Step 7: Identify Drops, Pickups, Travel, and Rehearsals
Review any production arrangements that involve breaks in engagement, travel, or rehearsal.
These statuses should be recorded separately when required by the production’s reporting system.
For example, a performer may finish a block of work, be released for a period, and return for additional scenes later. The DOOD should reflect that arrangement rather than representing the entire interval as one continuous hold.
Step 8: Calculate Working Days and Hold Days
Once all daily statuses have been entered, calculate the totals for each performer.
Common totals include:
- Total working days.
- Total hold days.
- Travel days.
- Rehearsal days.
- First working date.
- Last working date.
- Total engagement span.
These totals help producers and production accountants review the consequences of the current shooting schedule.
Do not combine all statuses into a single engagement total. A working day, a hold day, a travel day, and a rehearsal day may have different contractual and financial treatment.
Step 9: Review the DOOD Against Cast Agreements
Compare the report with the relevant performer agreements, deal memos, availability confirmations, and applicable union or guild requirements.
Check that:
- First and last working dates are accurate.
- Hold periods are correctly represented.
- Drop and pickup arrangements are permitted.
- Travel and rehearsal requirements are recorded.
- The correct cast members appear on each production day.
- Financial assumptions match the applicable agreements.
A DOOD is a scheduling reference, not a substitute for contractual review.
Step 10: Update the Report Whenever the Shooting Schedule Changes
Revisit the DOOD whenever scenes are moved, production dates change, or cast availability is revised.
A seemingly small schedule adjustment can affect several performers.
For example, moving a scene from Day 4 to Day 6 may create an additional hold day for one actor and extend another performer’s engagement.
The updated DOOD should reflect the approved shooting schedule and be made available to the relevant production and accounting personnel.
Day Out of Days Report Example: A Seven-Day Film Production
Consider a fictional independent film with four cast members working across a seven-day production schedule.
The production has a mixture of principal cast, supporting roles, and a day player.
The First Assistant Director uses the shooting schedule to prepare a cast DOOD.
Example Cast Requirements
| Cast ID | Character | Production requirements |
|---|---|---|
| 1 | Lena | Required on Days 1, 2, 4, 5, and 6 |
| 2 | Mark | Required on Days 1, 2, and 3 |
| 3 | Daniel | Required on Day 3 only |
| 4 | Sarah | Required on Days 2, 3, and 4 |
Example DOOD Grid
| Cast member | Day 1 | Day 2 | Day 3 | Day 4 | Day 5 | Day 6 | Day 7 |
|---|---|---|---|---|---|---|---|
| Lena | SW | W | H | W | W | WF | OFF |
| Mark | SW | W | WF | OFF | OFF | OFF | OFF |
| Daniel | OFF | OFF | SWF | OFF | OFF | OFF | OFF |
| Sarah | OFF | SW | W | WF | OFF | OFF | OFF |
Cast Engagement Summary
| Cast member | Work days | Hold days | First work day | Last work day |
|---|---|---|---|---|
| Lena | 5 | 1 | Day 1 | Day 6 |
| Mark | 3 | 0 | Day 1 | Day 3 |
| Daniel | 1 | 0 | Day 3 | Day 3 |
| Sarah | 3 | 0 | Day 2 | Day 4 |
The grid reveals that Lena has a hold day on Day 3 between two scheduled blocks of work.
The production team can review whether the Day 3 hold is necessary or whether the scenes involving Lena could be reorganized.
Mark finishes on Day 3, which means the remaining shooting days no longer require him according to the current schedule.
Daniel has a single-day engagement, represented by SWF.
Sarah starts on Day 2 and completes her scheduled work on Day 4.
The seventh day is an off day in this example. It is not counted as a working or hold day.
How to Interpret the Financial Implications
Lena’s example demonstrates why the DOOD matters beyond cast scheduling.
She has five scheduled working days and one hold day. The hold day may have financial implications depending on her agreement.
The producer and production accountant can review whether rearranging scenes would reduce the engagement period or eliminate an unnecessary hold.
However, the goal should not simply be to minimize the number of hold days. Any change must remain compatible with performer availability, location access, the shooting schedule, and contractual obligations.
The DOOD provides the visibility needed to evaluate those decisions.
How DOOD Hold Days Affect Film Production Costs
Hold days are one of the most important reasons production teams maintain a DOOD report.
A performer may not be required on set on a particular day but may still need to remain available to the production under the terms of their engagement.
This can create costs without producing additional footage.
Understanding the Difference Between Work Days and Hold Days
A work day is a day when the performer is scheduled to work. A hold day is a non-working day during which the performer remains engaged or reserved, subject to the applicable agreement.
Consider the following example:
| Cast member | Working days | Hold days | Total scheduled span |
|---|---|---|---|
| Actor A | 6 | 0 | 6 days |
| Actor B | 5 | 2 | 7 days |
| Actor C | 4 | 3 | 7 days |
Although Actor B and Actor C have fewer working days than their overall scheduled engagement spans, their hold arrangements may still affect the production budget.
The exact financial treatment depends on the relevant agreement, including applicable union or guild terms.
How Excessive Hold Days Create Scheduling Challenges
An extended hold period may occur when a production schedules scenes involving the same performer too far apart.
For example:
- An actor works on Day 1.
- The next scene involving that actor is scheduled for Day 5.
- The actor remains held on Days 2, 3, and 4.
If the shooting order can be adjusted without creating other scheduling problems, the production may be able to reduce that gap.
The First Assistant Director and production manager should consider whether moving compatible scenes closer together would make the engagement more efficient.
Review Hold Days Alongside Production Budgeting
Cast engagement costs should be reviewed alongside the wider production budget.
The production accountant can compare the scheduling information against performer agreements and approved financial estimates.
The DOOD makes the duration and gaps in cast engagements visible, while the budget provides the financial framework for reviewing their implications.
How to Optimize a DOOD Report for Better Cast Scheduling
A DOOD report is most useful when the production team reviews it alongside the shooting schedule rather than treating it as a document that only needs to be completed once.
Group Scenes Around Cast Availability
When preparing the stripboard, identify scenes involving the same performers and consider whether they can be scheduled closer together.
This can help reduce unnecessary gaps between working days.
The decision must also account for locations, other cast members, day and night requirements, and production complexity.
Review Long Engagement Spans
Identify performers whose first and last working days are separated by several non-working days.
Review these spans to determine whether the scheduling arrangement is necessary.
Long gaps may reflect genuine production requirements, but they should be visible to the producer and production accountant.
Examine Cast Requirements Across Each Shooting Day
A DOOD grid can also help production teams understand how many performers are required on each day.
This provides useful information for coordinating:
- Cast preparation.
- Makeup and wardrobe.
- Transportation.
- Holding areas.
- Catering.
- Accommodation for location shoots.
- Departmental preparation.
Compare DOOD Changes With Financial Estimates
When the shooting schedule changes, review the updated DOOD against the production’s financial estimates.
A revised scene order may affect engagement spans, hold days, travel requirements, and other costs.
Production accountants should review those changes against the actual contractual terms rather than assuming every additional day has identical financial treatment.
Common DOOD Report Mistakes to Avoid
1. Creating the DOOD before finalizing the shooting schedule
A DOOD prepared from an incomplete shooting schedule can contain incorrect working patterns and cast engagement dates. Use the approved schedule as the source.
2. Assigning hold days to every non-working day
Not every gap between production dates automatically represents a contractual hold. Check the actual performer engagement before assigning H.
3. Confusing off days with hold days
An off day is a non-production day. A hold day represents a performer being held between working engagements. These statuses should not be treated as interchangeable.
4. Using inconsistent status codes
Different scheduling systems may use different abbreviations. Establish the correct legend and maintain consistency throughout the report.
5. Ignoring travel and rehearsal requirements
Some performers may need to travel or rehearse before filming. Record these requirements where the reporting format supports them.
6. Failing to update the DOOD after schedule changes
Moving even one scene can alter the working pattern of several cast members. Reconcile the report whenever the approved shooting schedule changes.
7. Treating scheduled days as confirmed payroll amounts
The DOOD helps identify working and hold requirements, but actual payment depends on contractual arrangements and applicable production agreements. Do not use the report as a substitute for payroll verification.
8. Failing to review engagement spans
A performer may have a long gap between scheduled scenes. Review these periods to determine whether the shooting order can be improved without creating other production problems.
Day Out of Days Report Quality-Control Checklist
- The report uses the latest approved shooting schedule.
- Every cast member has the correct identification number.
- Cast requirements match the scenes assigned to each shooting day.
- Start Work entries are correct.
- Work and Work Finish entries are correctly assigned.
- Single-day engagements use the appropriate status.
- Hold days reflect actual engagement arrangements.
- Off days and hold days are distinguished.
- Drop and pickup periods are recorded where applicable.
- Travel and rehearsal requirements are included where needed.
- Total working days are calculated correctly.
- Total hold days are reviewed.
- First and last engagement dates are accurate.
- Performer agreements have been checked.
- Financial implications have been reviewed with production accounting.
- Schedule changes are reflected in the latest DOOD version.
How Studio Hero Can Help with Film Production Management and Scheduling
A DOOD report gives production teams a consolidated view of cast working patterns. Those requirements also need to remain connected to the wider production schedule, projects, people, resources, and financial records.
Studio Hero brings these operational activities together through its Production Management, Studio Scheduling, and financial management capabilities.
Connect Production Projects With Scheduled Work
Studio Hero’s Production Management feature connects Productions, Projects, Events / Sessions, and Tasks.
Project records provide a shared context for scheduled activities, talent, resources, supporting files, and financial information. This helps production teams organize the operational work associated with each production.
Coordinate People and Production Resources
Studio Hero’s Studio Scheduling connects production work with rooms, people, equipment, services, and resource availability.
This gives production teams a structured way to coordinate the resources needed for scheduled activities and review potential conflicts before committing to production work.
Keep Production Expenses Connected to Projects
Cast scheduling decisions can influence the wider production budget through performer engagements, travel arrangements, and other production requirements.
Studio Hero’s Studio Budgeting connects project expenses, purchase orders, rates, and financial records to the work being managed.
For production companies managing multiple film and video projects, Studio Hero’s Film Production Management Software provides a connected operating environment for production projects, scheduling, resources, and financial operations.
Wrapping Up
A Day Out of Days report makes cast scheduling easier to review by showing each performer’s working status across the entire production. It brings start dates, working days, hold periods, and finish dates into one view, helping assistant directors, producers, and production accountants identify scheduling gaps and evaluate engagement requirements.
A useful DOOD must remain consistent with the approved shooting schedule and the actual performer agreements. Every scene move, cast availability change, or revised production date should be reflected in the report.
When the shooting schedule and DOOD are reviewed together, production teams have a clearer understanding of cast commitments, potential hold costs, and the scheduling decisions that affect the production budget.